Project timeline

We have outlined a high level plan that shows the key activities that will be happening and when.

Dates are always subject to change, depending on a number of factors, but we will try to stick to them as much as we can, and update you of any changes as we progress.

Important dates

View important dates for the Alton regeneration project:

2025

  • October: Ballot Decision
  • November: Improvement works start on Alton Activity Centre & Downshire Field playspaces
  • December:
    • Early Improvement Plan submitted for Planning
    • Murals across the estate completed
    • Detailed design of masterplan
    • Preparation of Early Improvement Plan site

2026

  • Spring:
    • Local elections
    • Installation of a new ‘Welcome to Alton’ gateway sign
    • Leisure centre linkway artwork installed
    • Wayfinding and heritage trails completed
    • Foodwaste bins programme roll out
  • Summer:
    • Alton Activity Centre & Downshire Field playspaces open
    • New creative lighting projects installed
  • Winter: Focus Hall refurbished and re-opened

2027

  • Early Spring:
    • Start on site - Early Improvement Plan - Community Hub
    • Masterplan submitted for Planning
  • Summer: Start on site - Early Improvement Plan - Residential building

2028

  • Spring: Planning Committee - Masterplan
  • Winter: Completion - Early Improvement Plan - Community Hub

2029

  • Summer:
    • Completion - Early Improvement Plan - Residential building
    • Portswood Place start on site

2030

  • Spring: Danebury Square and Retail Parade start on site
  • Early Summer: Local elections

2031

  • Early Summer: Portswood Place completion

2032

  • Late Autumn: Danebury Square and Retail Parade completion