Project timeline
We have outlined a high level plan that shows the key activities that will be happening and when.
Dates are always subject to change, depending on a number of factors, but we will try to stick to them as much as we can, and update you of any changes as we progress.
Important dates
View important dates for the Alton regeneration project:
2025
- October: Ballot Decision
- November: Improvement works start on Alton Activity Centre & Downshire Field playspaces
- December:
- Early Improvement Plan submitted for Planning
- Murals across the estate completed
- Detailed design of masterplan
- Preparation of Early Improvement Plan site
2026
- Spring:
- Local elections
- Installation of a new ‘Welcome to Alton’ gateway sign
- Leisure centre linkway artwork installed
- Wayfinding and heritage trails completed
- Foodwaste bins programme roll out
- Summer:
- Alton Activity Centre & Downshire Field playspaces open
- New creative lighting projects installed
- Winter: Focus Hall refurbished and re-opened
2027
- Early Spring:
- Start on site - Early Improvement Plan - Community Hub
- Masterplan submitted for Planning
- Summer: Start on site - Early Improvement Plan - Residential building
2028
- Spring: Planning Committee - Masterplan
- Winter: Completion - Early Improvement Plan - Community Hub
2029
- Summer:
- Completion - Early Improvement Plan - Residential building
- Portswood Place start on site
2030
- Spring: Danebury Square and Retail Parade start on site
- Early Summer: Local elections
2031
- Early Summer: Portswood Place completion
2032
- Late Autumn: Danebury Square and Retail Parade completion