Further information about Winstanley and York Road

Timeline for development

The regeneration scheme will be completed in phases so some parts of the estate will be rebuilt before others. New homes will be built before blocks are demolished, so households can move straight into their new permanent home. This approach means that most tenants and leaseholders will only be required to move once.

Our aim is to deliver the scheme as quickly as possible, and the outline timeline below gives an approximate indication for the construction of the first new homes.

Main site Satellite sites
2015

June 2015 - onwards
Tenants offered 'early move'
options

In-depth conversations with
residents of the Winstanley
and York Road estates

Offer to purchase properties
from leaseholders

2015
Satellite sites identified





2016

January 2016
We began procurement
for a Joint Venture (JV) partner

Early 2016
Design teams selected

Summer 2016
Consult on development
design and build

2017

Early 2017
We selected a JV partner

Early 2017
Consultation starts on Inkster
and Penge refurbishment

Early 2017
Obtain planning permissions
and select contractor

Summer 2017 Phasing Plan published

Summer 2017
JV works up first planning
permission for regeneration area

Autumn 2017
Building work starts on
Battersea High Street,
Gideon Road, Tyneham Close
& Lavender Hill

2018

Early 2018
Work starts on Inkster and
Penge refurbishment

Building commences on main
site including the new leisure
centre, community centre,
library and Grant Road

Summer 2018
Commence building
first homes on main site

2019

Early 2019
First moves into new homes on satellite sites

Please note - this is an indicative programme only at this time before a detailed phasing plan is published.