BSF timeline

The timetable for key stages of the BSF programme

BSF stage   Process   Timescale  Progress 
 
Programme Initiation Preparation for BSF Project team is established and initial consultation takes place with schools September 2007 Remit meeting with Department for Children, Schools and Families (DCSF) held 20 September 2007
Strategic Planning Strategy for Change Part 1 Proposals agreed about what needs to be done across the borough and the expected outcomes of BSF in Wandsworth November 2007 Strategy for Change Part 1 was submitted 15/11/2007 and approved in January 2008 
Strategy for Change part 2 Strategy developed for how the proposals in part 1 will be delivered

November 2007 

to

September 2008

 
Schools Strategy for Change Each school develops plans about how their school will change as a result of BSF.
Strategy for Change part 2 submitted to Partnerships for Schools (PfS)

September 2008

Strategy for Change part 2 was submitted on 19 September
Making the Business case Outline Business Case (OBC) developed setting out the scope, cost, affordability, risks, procurement route and timetable of the project. Autumn 2008 to Spring 2009

 

OBC submitted April 2009

Planning for Procurement Prepare documentation and evaluation criteria using standard procurement and contractual documents provided by PfS Summer 2009  
Agree wording and scope of Official Journal of the European Union (OJEU) notice
Bidder selection Publish OJEU/Pre Qualification Questionnaire  (PQQ)

Summer 2009 -summer 2010

 

OJEU published on 24th July 2009

For more information visit the procurement page

PQQ return deadline 5pm on 3rd September 2009

Bidders Day for potential bidders
Bidders submit PQQ and shortlist to three bidders
Competitive Dialogue phase 1 and shortlist to two bidders

Competitive Dialogue phase 2. Short-listed bidders asked to submit their final bids

Contractual/Commercial Close Final bids are evaluated and preferred bidder is appointed Winter  2010  
Final Business Case is submitted to DCSF
Local Education Partnership established and financial close
Construction Phase Work starts with sample schools first. Spring 2011 onwards